Package G

Plantation re-establishment

A sequence rather than a machine: stump treatment, then slash treatment, then tillage, scarification or mounding, then planting. Measured in hectares and planting spots, not cubic metres.

Primary KPI: $/hectare completed to the establishment specification

The brief

What this fleet is built to do

This is a sequence rather than a machine. Stumps are treated, slash is treated, the soil is tilled, scarified or mounded, and then the site is planted — and each step constrains the next. A site prepared poorly cannot be planted well, and a planting window missed cannot be recovered later in the year.

That window is the governing constraint. Site preparation must be finished before planting, planting must happen in conditions the seedlings will survive, and the client's schedule is set by the season rather than by contractor availability. A machine that is 20% faster but arrives after the window closes has no commercial value at all.

The dominant cost variable is the ground rather than the vegetation. Rock content and stump density determine tooth wear, gearbox loading and achievable hectares per day, and neither is visible from a brochure or reliably described in a tender document. Survey discipline is what separates contractors who hold their quoted cost per hectare from those who do not.

Configuration

The system

Typical fleet

  1. 1Stump treatment (shear, grinder or tiller)
  2. 2Slash treatment (mulcher)
  3. 3Tillage / scarification / mounding
  4. 4Mechanised or manual planting

Specification drivers

Priorities

  • Hectares per day inside the establishment window
  • Planting spots per hour
  • Soil condition and compaction relief
  • Rock tolerance

Measurement

How this work is sold

Primary KPI

$/hectare completed to the establishment specification

Model it in the cost calculator →

What goes wrong

The trap in this package

The constraint

What actually sets production here

Every fleet produces at the rate of its slowest element and pays for all of them. This is where that element usually sits in this package.

The bottleneck

Hectares completed inside the establishment window

Revenue is bounded by the window, not by annual machine capacity. Capacity above what the window can absorb earns nothing, and a breakdown in week two cannot be made up in week eight because there is no week eight.

How it shows up

A schedule with no weather allowance, or a fleet sized against annual hectares rather than against working days in the window.

What to do about it

Divide the contracted hectares by the working days the window actually contains, add weather and breakdown allowance, and resource to that number.

Sizing

The questions that size this fleet

Each one has an answer specific to your sites. A default taken from someone else's operation is where imbalance starts.

1

How many machines does the window need?

Contracted hectares divided by working days available, plus an allowance for weather and breakdown days appropriate to the region. This almost always exceeds what an annual-capacity calculation suggests, which is why contracts get under-resourced.

2

Which ground-preparation method applies?

Whichever the silvicultural prescription specifies — mounding for drainage, ripping for compaction, scarification for competition, full tillage for residue incorporation. The prescription belongs to the client and the site; the method determines the machine, not the reverse.

3

How is stump treatment handled?

By shear, grinder or tiller depending on stump density, what the following operation needs, and whether the stump material has a biomass outlet. On conversion sites with high stump density this step can dominate the sequence.

4

What consumable stock does a campaign need?

The campaign's expected wear parts, on site before it starts. A two-day wait for tiller teeth in week three of a six-week window is unrecoverable, which makes pre-stocking cheap insurance rather than working capital tied up.

Conditions

What to change when your site is different

The package above assumes a typical case. These are the departures that change the configuration rather than just the rate.

IfChangeBecause
High rock contentChange tooth and tool-holder selection, raise the consumable budget, and reduce the assumed hectares per day.Rock drives consumption and slows progress simultaneously, so the cost per hectare moves from both directions at once.
High stump density on conversion sitesWeight the fleet toward stump treatment before tillage capacity.Stumps constrain every following operation, and tillage capacity that cannot be fed by stump treatment sits idle in a window that does not wait.
Heavy slash loadsAdd mulching capacity ahead of tillage.Residue that has not been reduced fouls tillage equipment and slows the operation that the window is tightest on.
Wet or compaction-prone soilsPrioritise mounding and compaction relief, and build a larger weather allowance into the schedule.Wet ground stops site preparation and planting outright, so weather days are a schedule input rather than an exception.

Capital

How to get here without buying it all at once

Very few contractors start at the full configuration, and the ones who do are usually carrying more capital than their contracted work supports.

Phase 1

Single implement behind existing plant

A mounder, ripper or scarifier operated behind a tractor or dozer already in the business.

Lowest exposure; suits testing whether regional campaign volume supports dedicated capacity.

Phase 2

Dedicated site-preparation unit

A carrier with a forestry tiller or stump cutter, plus a second implement for the same carrier.

Where rock content stops being a curiosity and becomes the main commercial risk.

Phase 3

Full establishment capability

Site preparation, planting machinery and mechanical pruning, resourced for a multi-estate campaign.

Justified by contracted hectares across more than one client, so a deferral on one estate does not idle the fleet.

Avoid

Savings that cost more than they save

Pricing hectares without surveying rock

Tooth and tool-holder wear on rocky ground can exceed the entire consumable allowance in a quote, and no brochure figure or tender document will warn you. Walking representative ground before pricing is cheap by comparison.

Sizing the fleet against annual capacity

Establishment revenue is bounded by weeks, not months. A fleet that could complete the hectares in a year and cannot complete them in the window has under-resourced the contract.

Carrying no consumable stock into a campaign

Parts ordered mid-campaign arrive against a clock that does not stop. The holding cost of a campaign's wear parts is small against the days they protect.

Treating weather days as an exception

Wet ground stops the work. A schedule with no weather allowance will be late, and lateness here means unplanted hectares rather than a deferred invoice.

Suppliers

Brands to evaluate

Detail

Machine classes in this package

Questions

Common questions about this package

Why do establishment contractors talk about windows rather than hours?

Because the work cannot be moved. Site preparation has to precede planting, and planting has to happen in the conditions seedlings will survive, so the available working days are set by the season rather than by demand. That makes hectares per window the relevant capacity question, and it makes a mid-campaign breakdown far more expensive than the same breakdown would be in harvesting.

How much does rock content change tilling cost?

Enough to invert the economics of a job, though the multiple varies too widely by soil type and tooling for a general figure to be honest. The mechanism is what to plan around: rock drives tooth and tool-holder replacement and increases gearbox loading while reducing hectares per day, so cost per hectare rises as production falls. This is why surveying before pricing is standard among contractors who stay profitable.

Should the stumps be sheared, ground or tilled?

It depends on stump density, what the following operation needs and whether the material has a biomass outlet. Shearing suits recovery and removal; grinding suits reducing individual stumps in place; tilling incorporates residue where the prescription calls for a prepared planting medium. The stump systems chapter sets out the trade-offs, but the silvicultural prescription usually narrows it before machine choice enters.

Is it worth owning planting machinery for a short season?

Only if the hectares justify it across more than one client, or the carrier earns in another season. Machinery used in a single annual campaign carries twelve months of depreciation, finance and insurance against a few weeks of revenue. Many established contractors own site-preparation capability, which spreads across a longer period, and subcontract or hire planting capacity.